The Site and Its Munitions History

Bandeath was an Admiralty munitions depot for more than sixty years. That history makes unexploded ordnance and contamination certain lines of enquiry. Both can be managed for an industrial use like a data centre.

A depot on the Forth

Bandeath became an Admiralty depot in the First World War and stayed in use through the Second World War as a Royal Naval Armament Depot. More than 30 warehouses sat inside earth blast walls, linked by an internal railway to a pier where munitions were loaded onto river craft to resupply Royal Navy ships. The Ministry of Defence sold the site in 1978. It was refurbished in the early 1980s and has been run as a Council industrial estate since.

Surviving features include warehouses, air-raid shelters, a pillbox, watch posts and distinctive firewatch posts. Any development should record and respect this heritage, which is part of the story of the Forth and its communities.

What the history means for building

HazardLikely sourcesHow it is dealt with
Unexploded or lost ordnanceMagazines, rail sidings, the pier and levelled blast wallsA detailed UXO risk assessment, magnetometer surveys and a specialist watching brief
Explosive residuesSoils around magazines and handling areasSite investigation with explosives-specific testing; remove hotspots
Heavy metalsMunitions handling and railway ballastAssess against commercial standards; cap under hardstanding
Fuels and PCBsRail and crane fuels, old transformersTargeted excavation and treatment
AsbestosWartime buildings and the 1980s refurbishmentAsbestos survey before any works
Coal-mining legacyPossible Polmaise workings at depthCoal-mining risk report; grouting only if shallow workings are found
Soft estuarine claysThe lower estate beside the ForthPiled foundations to firm ground

Why a data centre suits a contaminated site

A data centre is a commercial use with almost the whole site under buildings and hardstanding. There are no gardens, homes or food growing, so the clean-up standard is far less onerous than for housing. The clean-up can be combined with raising ground levels against flooding, using a clean cap of imported material.

The developer, not the Council, should carry out and pay for the clean-up through planning conditions: a desk study, site investigation, remediation strategy and verification report.

Indicative cost allowances (49 MW, about 6 hectares)

ItemAllowance
Desk studies: UXO, contamination, mining and asbestos£30k–£60k
Intrusive site investigation£150k–£300k
UXO survey, watching brief and clearance£150k–£600k
Remediation and capping£1.0m–£3.0m
Piling and ground improvement£1.5m–£4.0m
Total abnormal allowanceabout £3m–£8m

These are allowances before any investigation, not quotations.