The proposal asks Stirling Council to scope its land at the lower end of Bandeath Industrial Estate, Throsk, for a mid-sized data centre that supplies heat to local homes and pays a legally binding share of its income to the surrounding villages.
Why Bandeath?
Bandeath sits inside a meander of the River Forth, about three miles east of Stirling on the A905. It is an established Council industrial estate, zoned for employment and industrial use, and the lower end has no housing beside it. Few sites in central Scotland combine all of these:
- Brownfield industrial land already in public ownership
- No homes immediately next to the development area
- The River Forth and the flooded Polmaise coal workings for cooling and heat storage
- Proximity to the Beauly–Denny transmission corridor
- Three villages close enough to use the waste heat
What is being proposed
The recommended scheme is a 49 MW “green compute and heat” campus, about 39 MW of computing load on roughly 15 acres. It would be paid for entirely by private investment of about £315m. The Council would provide the land on a long lease and keep control as landlord.
Staying just under 50 MW means the application is decided locally rather than notified to Scottish Ministers. It also means the scheme can probably connect to the local electricity network rather than queueing for a transmission connection.
The original request
The proposal began with an email from Councillor Alasdair MacPherson to the Chief Executive of Stirling Council in November 2026:
Can we discuss looking at doing a scoping exercise on land the Council own at Bandeath Industrial for an AI datacentre?
I’m convinced there is a great opportunity here for the Council as the developers could use minewater thermal energy and other renewables to power it. The bottom end of this site is close to the River Forth which offers untapped renewable opportunities too. The proximity of the Beauly to Denny pylons would also be beneficial.
I’m only too aware that there is growing opposition to AI datacentres – but if you get the location right and you can demonstrate significant community benefit, some community – and the Council – could hit the jackpot. There could be huge potential for local jobs, district heating schemes and also income from renewables.
The bottom end of Bandeath Industrial estate offers a unique opportunity given there is no housing in close proximity. This will take political leadership to sell it – but I’m up for trying it before I step down in May.
What the feasibility study found
- The location works. Bandeath is brownfield, zoned for industry, and has no housing at the lower end.
- Power must come from the grid. Minewater and the Forth are heat and cooling assets. Their value is cheaper cooling, heat storage and low-cost heat for the villages.
- Land ownership must be checked first. The largest open plot on the estate, 45.56 acres, belongs to Bandeath Holdings Ltd, not the Council.
- The munitions history and flood plain can be managed, but they shape the layout and add an estimated £3–£8m in abnormal costs.
- Business rates mostly don’t stay local. Scottish non-domestic rates are pooled nationally, so the Council’s secure income is ground rent plus a share of any energy and heat company.
- No decision is possible before May 2027. Holyrood has backed a pause on data centre decisions until national guidance is published.
What happens next
- The Council commissions a scoping report on a 25–49 MW campus.
- Officers map the Council’s freehold and talk to Bandeath Holdings Ltd about its land and 26 MVA power supply.
- SP Energy Networks is asked for grid connection estimates.
- Flood modelling with SEPA and desk studies on unexploded ordnance, contamination and coal mining are commissioned.
- The Fallin minewater study is extended to cover a Throsk–Fallin–Cowie heat network.
- The Council adopts a data centre community-benefit policy before the 2027 pre-election period.
- Drop-in sessions are held in Throsk, Fallin and Cowie.