Proposal · Bandeath Industrial Estate, Throsk

Bandeath Green Compute & Heat

A proposal for a 49 MW data centre at Bandeath that puts cheaper heat, lower energy bills and a fair share of the profits in the hands of Throsk, Fallin and Cowie.

Proposal update · 19 November 2026 · Pre-feasibility study

Read the proposal → See the key figures

What the proposal could mean for local people

Bandeath was an Admiralty munitions depot for more than sixty years. Today the lower end of the estate sits beside the River Forth with no housing next to it, close to Scotland’s main north–south electricity route. This proposal asks Stirling Council to test whether that land could host a mid-sized, heat-producing data centre built around the needs of the surrounding villages.

£1.225m a yearCommunity benefit fund at 49 MW, index-linked and legally binding
Up to £1.8m a yearIf the fund is linked to 3% of the campus’s gross revenue
£1,150–£1,250Estimated yearly saving for every Throsk household
60–100 jobsPermanent local jobs, with priority recruitment from the three villages

All figures are desk-based estimates (±50%) from a pre-feasibility study. They must be tested by Council officers, SEPA, SP Energy Networks and specialist surveys before any decision is made.

Who benefits

The community fund would be shared between the three villages most affected by the development, based on how close each is to the site and how much each would be affected by it.

Host community · 50%

Throsk

£612,500 a year at 49 MW. First on the heat network, with an annual energy-bill credit for every household and a legacy fund for the future.

Closest village · 40%

Fallin

£490,000 a year at 49 MW. Heat-network connections, warm-homes grants, apprenticeships and support for Fallin’s minewater and community energy projects.

Visual impact · 10%

Cowie

£122,500 a year at 49 MW. Tree planting and screening, community grants and skills bursaries.

How the community fund would work →

How it would work

Power from the grid

A data centre of this size runs on grid electricity, largely Scottish wind power, and connects through the local network. Minewater and the river cannot power it, but they can make it far more efficient.

Waste heat for local homes

Servers produce a steady supply of low-grade heat. Heat pumps can raise it to warm homes through a district heat network, starting with Throsk and Fallin.

Minewater and the Forth

The flooded Polmaise workings and the River Forth can cool the halls without evaporating water, and the old workings can store summer heat for winter.

A binding community deal

Payments are secured by a Section 75 agreement and the Council’s lease, index-linked, paid from the start of construction, and rising automatically if the campus grows.

Read about power, heat and renewables →

Facing the hard questions

Opposition to AI data centres is growing across central Scotland, and much of it is well founded. The proposal tackles the main concerns directly.

Where things stand

  1. Now to May 2027. Ask the Council to commission a scoping study and adopt a community-benefit policy.
  2. 2027. National data centre planning guidance is published. The scheme is tested against it.
  3. 2027–28. Developer selection and at least 12 weeks of community consultation.
  4. 2028–29. Planning application, with the Section 75 agreement and lease signed together.
  5. 2029–31. Construction, first power and the heat network to Throsk and Fallin.

About this website

Published by Councillor Alasdair MacPherson

If you get the location right and you can demonstrate significant community benefit, some community – and the Council – could hit the jackpot.

This website sets out a proposal raised with the Chief Executive of Stirling Council. It is a discussion paper, not a Council decision.

Updated 19 November 2026