Power, Heat and Renewables

Electricity for the campus has to come from the grid. Minewater and the River Forth turn the campus into a heat supplier for the villages, and that is what makes Bandeath different.

Connecting to the grid

A 49 MW campus uses about 400 GWh of electricity a year, far more than any on-site renewable here could produce. Being close to the Beauly–Denny pylons helps with routing, but a data centre cannot tap a 400 kV line directly. It connects through a substation, which SP Energy Networks and the National Energy System Operator would have to approve.

A 26 MVA green power supply has already been promised to a neighbouring plot at Bandeath. That suggests a 25–49 MW scheme could connect through the local distribution network, outside the congested national transmission queue.

What each resource can realistically do

ResourceWhat it can doValue to the scheme
Minewater (Polmaise workings)A steady, cool heat source and sink. It can cool the halls in summer and store waste heat for winter. It generates no electricity.High: builds on Fallin’s minewater feasibility work
River ForthRiver-source cooling and heat pumps. A river-source heat pump already has planning consent at Bandeath. Tidal power is not viable in this stretch.High for cooling and heat
Data centre waste heatLiquid-cooled servers give off heat at 30–50°C, which heat pumps can raise to 70°C for homes.Very high: the community-benefit engine
Solar on spare Council land and roofsAbout 10 MWp, supplied by private wire to the campus.Medium: Council and community income
Battery storageSmooths load swings and earns grid-balancing income.Medium
The gridSupplies 95% or more of the power, largely from Scottish wind.Essential

A heat network for Throsk, Fallin and Cowie

Heat-network pipework costs roughly £3,000–£5,000 a metre, so every kilometre matters. Throsk is beside the estate, Fallin is about 2.5 km away and Cowie is further. A phased network makes sense:

  1. Phase 1: Throsk, the cheapest and quickest connection.
  2. Phase 2: Fallin, linking with the Fallin minewater project.
  3. Later phase: Cowie, if the costs stack up.

The developer should pay for the heat-recovery plant, with the network built with support from the Scottish Government’s Heat Network Fund. Connected households would be guaranteed heat at least 10% below the gas or electric equivalent.

Water use

The campus would use closed-loop cooling with river and minewater heat exchange, not evaporative cooling towers. Industry figures put the initial fill of a closed-loop system at roughly the annual water use of 44 homes, with low ongoing use after that.